PHARMACEUTICAL

Ivy Animal Health Solid Dosage

The project involved the renovation of an existing 6,000 square-foot building, renovation of specific areas of an adjacent 6000 square-foot building, as well as work in an off-site location.

Lab Relocation - To make way for the Manufacturing Cell construction, this project involved relocating the QC Laboratory to an off-site location.

Packaging - A new Packaging Site was constructed within an existing facility.  This is a Class 100 space with once-through ventilation to allow for multiple product packaging.

Manufacturing Cell - This phase of the project consisted of a new 3,500 square-foot Class 100 manufacturing cell. The HVAC system was designed with a single pass air system for multiple product manufacturing. Supply air is terminal HEPA filtered and the return is routed through a dust collection system prior to being discharged into the atmosphere.

Compudose Manufacturing Cell - The HVAC system is recirculating for dedicated product manufacturing. Supply air is terminal HEPA filtered at the individual rooms and the return is routed through a central HEPA filter bank located at the air handling unit.